Hub You
#1 in Business Subscribe Email Print

You are here: Home > Business > Management > Risk Management - Managing Milestones

Tags

  • catch
  • ready
  • cover
  • plans might
  • software engineering
  • worse failing

  • Links

  • Basic Credit Card Shifting
  • FHA Refinancing May Save Your Home
  • Risks and Benefits of Tax Lien Investing
  • Hub You - Risk Management - Managing Milestones

    Poor Performance - Your Options For Dealing With It Effectively
    Poor performance is an issue that faces any manager from time to time. You can deal with it in several ways:• Put up with it (not to be recommended)• Re-brief or train to allow performance to improve.• Re-assign the person to another task that they can do.• Terminate employment.These options are linke
    course, have a cost but this must be weighed up against the possibility of delaying the milestone payment and worse, failing to meet the milestone timescale. Once one milestone is late, it's very hard to catch up and much rescheduling is needed in order to still meet the end delivery date. Failing to meet milestones is usually very unpopular with the Customer and not at all likely to do the company’s reputation any good.

    On the up side, if a risk does NOT impact and the milestone

    Data Warehousing - Tom's Ten Data Tips
    Data Warehousing was an innovation from the 90's that promised to change the data landscape for good. How far have we come? Many vendors have entered the marketplace because it makes sense to bring together data from throughout the organization, and this will continue to make sense in the future.How large the Data Warehouse marke
    Part of planning for risk involves allocating each identified risk to a project milestone. Very often a milestone is attached to a payment, so a risk can also have an accurate value attached to it. By its nature, each risk will impact, if at all, at a certain time. For example, Milestone 1 is "Delivery of Software X, Issue A to the Customer".

    If this risk impacts, we will not receive the Milestone 1 payment from the Customer. This payment has been planned to cover costs of staffing, materials, sub-contractor payments and a variety of other project expenses including finance charges up to this point. The cost of this risk, or any other associated with this Milestone, impacting is basically the cost of borrowing that amount of money, from the time it should have been received up until the time when it is actually received.

    In order to manage this risk, regular project meetings will be held, a part of which will cover the progress of identified risks. The risk owner will report on each risk with their assessment of the likelihood its occurring. If the likelihood of any risk impacting increases, steps will be taken to implement the mitigation measures already identified.

    In the case of this example, the mitigation measures might be "Introduce interim acceptance testing to identify problems early".

    Let us assume that the introduction of this mitigation measure has become necessary and the interim acceptance testing has shown that the software is far from ready for delivery. This will mean that fall-back or contingency plans must be implemented.

    This is a very undesirable state of affairs but such plans might be: "Introduce additional software engineering effort to identify and resolve bugs" or, assuming we don't have the personnel available to throw extra resources at the problem "Put project software engineers on overtime in order to identify and resolve bugs".

    In themselves, these contingencies will, of course, have a cost but this must be weighed up against the possibility of delaying the milestone payment and worse, failing to meet the milestone timescale. Once one milestone is late, it's very hard to catch up and much rescheduling is needed in order to still meet the end delivery date. Failing to meet milestones is usually very unpopular with the Customer and not at all likely to do the company’s reputation any good.

    On the up side, if a risk does NOT impact and the milestone w

    Why Is Management Needed
    To achieve objectives, managers need to maintain the balance among the conflicting demands of the stakeholders of an organization. Stakeholders are all those, who have a stake in an organizational success, including employees, owners, customers, creditors and others. Owners seek a satisfactory return on their investment; employees want
    ng, materials, sub-contractor payments and a variety of other project expenses including finance charges up to this point. The cost of this risk, or any other associated with this Milestone, impacting is basically the cost of borrowing that amount of money, from the time it should have been received up until the time when it is actually received.

    In order to manage this risk, regular project meetings will be held, a part of which will cover the progress of identified risks. The risk owner will report on each risk with their assessment of the likelihood its occurring. If the likelihood of any risk impacting increases, steps will be taken to implement the mitigation measures already identified.

    In the case of this example, the mitigation measures might be "Introduce interim acceptance testing to identify problems early".

    Let us assume that the introduction of this mitigation measure has become necessary and the interim acceptance testing has shown that the software is far from ready for delivery. This will mean that fall-back or contingency plans must be implemented.

    This is a very undesirable state of affairs but such plans might be: "Introduce additional software engineering effort to identify and resolve bugs" or, assuming we don't have the personnel available to throw extra resources at the problem "Put project software engineers on overtime in order to identify and resolve bugs".

    In themselves, these contingencies will, of course, have a cost but this must be weighed up against the possibility of delaying the milestone payment and worse, failing to meet the milestone timescale. Once one milestone is late, it's very hard to catch up and much rescheduling is needed in order to still meet the end delivery date. Failing to meet milestones is usually very unpopular with the Customer and not at all likely to do the company’s reputation any good.

    On the up side, if a risk does NOT impact and the milestone

    What is Factoring Financing?
    Do you have clients that take 30, 50 or 60 days to pay their invoices? Although having slow paying clients is expected in today’s business environment, they make managing cash flow a very difficult task. Paying suppliers, salaries and rent becomes a challenge.However, there is a way to solve this problem. The solution involves fa
    k owner will report on each risk with their assessment of the likelihood its occurring. If the likelihood of any risk impacting increases, steps will be taken to implement the mitigation measures already identified.

    In the case of this example, the mitigation measures might be "Introduce interim acceptance testing to identify problems early".

    Let us assume that the introduction of this mitigation measure has become necessary and the interim acceptance testing has shown that the software is far from ready for delivery. This will mean that fall-back or contingency plans must be implemented.

    This is a very undesirable state of affairs but such plans might be: "Introduce additional software engineering effort to identify and resolve bugs" or, assuming we don't have the personnel available to throw extra resources at the problem "Put project software engineers on overtime in order to identify and resolve bugs".

    In themselves, these contingencies will, of course, have a cost but this must be weighed up against the possibility of delaying the milestone payment and worse, failing to meet the milestone timescale. Once one milestone is late, it's very hard to catch up and much rescheduling is needed in order to still meet the end delivery date. Failing to meet milestones is usually very unpopular with the Customer and not at all likely to do the company’s reputation any good.

    On the up side, if a risk does NOT impact and the milestone

    Trade Show Booth Tear-Down
    After a show wraps, your entire booth staff will want to leave as soon as possible. Some may even book return flights that coincide with the end of the show. Avoid laying the burden of tear-down, packing and shipping on one person. In your pre-show planning, be sure that staff time and travel allows for adequate booth tear-down, packing
    software is far from ready for delivery. This will mean that fall-back or contingency plans must be implemented.

    This is a very undesirable state of affairs but such plans might be: "Introduce additional software engineering effort to identify and resolve bugs" or, assuming we don't have the personnel available to throw extra resources at the problem "Put project software engineers on overtime in order to identify and resolve bugs".

    In themselves, these contingencies will, of course, have a cost but this must be weighed up against the possibility of delaying the milestone payment and worse, failing to meet the milestone timescale. Once one milestone is late, it's very hard to catch up and much rescheduling is needed in order to still meet the end delivery date. Failing to meet milestones is usually very unpopular with the Customer and not at all likely to do the company’s reputation any good.

    On the up side, if a risk does NOT impact and the milestone

    Why A Business Plan Is So Important For Your Success
    If you have decided to start your own business, one of the first things that you need to do is to work on a business plan. A business plan is so important because it actually serves as a compass for the direction your business will take in the future. Having a plan will also help you achieve the things you want to achieve and will help
    course, have a cost but this must be weighed up against the possibility of delaying the milestone payment and worse, failing to meet the milestone timescale. Once one milestone is late, it's very hard to catch up and much rescheduling is needed in order to still meet the end delivery date. Failing to meet milestones is usually very unpopular with the Customer and not at all likely to do the company’s reputation any good.

    On the up side, if a risk does NOT impact and the milestone with which it is associated is met, that risk can be deleted and forgotten, leaving time and space to concentrate on the next one.

    Next in this series, we'll look at managing the risks associated with suppliers or sub-contractors.

    HTTP = HTML link (for blogs, profiles,phorums):
    <a href="http://www.iadvice.info/article/23351/iadvice-Risk-Management--Managing-Milestones.html">Risk Management - Managing Milestones</a>

    BB link (for phorums):
    [url=http://www.iadvice.info/article/23351/iadvice-Risk-Management--Managing-Milestones.html]Risk Management - Managing Milestones[/url]

    Related Articles:

    Good Manners Enhance Your Chances of Success in Your Career

    Parasites of the Business World

    Business Ethics: Functional Choices

    Bookmark it: del.icio.us digg.com reddit.com netvouz.com google.com yahoo.com technorati.com furl.net bloglines.com socialdust.com ma.gnolia.com newsvine.com slashdot.org simpy.com shadows.com blinklist.com